StrongForce Malaysia have been awarded the Post Tension package for Viaduct Package V7 of the new rail based public transport system currently underway in the Klang Valley region in Greater Kuala Lumpur.

Engaged by Main Contractors Persys Sdn Bhd a subsidiary of the MTD Group, the construction will be carried out from Bandar Tun Hussein to Taman Mesra.

Using the StrongForce multi-strand system approximately 900 Ton of post tension strand will be installed into the elevated segmented box girders. Set for completion in the second quarter of 2017 the project will total 3.6 Km in length and will consist of 105 spans.

 

Recent News


Rudloff-StrongForce brings post-tension innovation to Islamabad’s tallest residential complex
Rudloff-StrongForce (RSF) is proud to be delivering the post-tension design-and-construct solution for Mount Khalid — a landmark, four-tower residential development...
Reem Island Bridge Advances Abu Dhabi’s 2030 Vision
RSF has successfully delivered the post-tension scope for the Reem Island Bridge (Bridges 7 & 8), connecting Reem Island to...
Rudloff StrongForce and Gardinia Announce Strategic Post-Tensioning Agency Partnership
Rudloff StrongForce (RSF) is pleased to announce the signing of an exclusive system supply partnership with Gardinia Prestressed Concrete, the...
Rudloff-StrongForce Brazil Awarded Post-Tensioning Package for Major São Paulo Infrastructure Project
Rudloff-StrongForce has been appointed to deliver the full post-tensioning scope for the Northern Section of the Rodoanel (Ring Road) in...
Rudloff-StrongForce Supports the Landmark Capital Diamond Tower in Egypt
Rudloff-StrongForce International is proud to be a key post-tensioning system provider for the Capital Diamond Tower, a groundbreaking development in...

United Arab Emirates

Contact
Interactive Map

Where We Work

Since 1965, we’ve partnered with clients in over 50 countries across six continents—delivering more than 600 civil structures, over 24 million square metres of building works, and 700+ wind towers. Our optimised engineering solutions improve project efficiency, enhance construction methods, and support global sustainability goals.

World Map

Rudloff StrongForce Locations

Rudloff StrongForce System Supply

Worked In
16
 Countries
System Supply
50
 + Countries
Building Structures
26
 Million+ m²
Civil Infrastructures
600
 + Projects
Wind Towers
850
 + Projects
Building Rehabilitation
350
 + Projects
© 2025  Rudloff StrongForce. All Rights Reserved.