With the site works in full swing, Strongforce have now successfully completed 16 of the 20 bridges on Package 2 of the Expo 2020 roading upgrades. To date over 1,000 ton of post tension strand has been installed at an average of 120 ton per month, with multi-strand tendons reaching up to 210 metres in length.
Initially set for completion November 2019, the project’s revised program has been pushed forward for a September 2019 completion.
Providing project planning, technical detailing and onsite specialist works for the full post tension scope, StrongForce has been a major contributor in ensuring main contractor “China State” was able to accelerate works on the initial project program buy over 8 weeks, bringing the project in well ahead of program.
With Expo 2020 expecting over 25 million visitors, the infrastructure will play a critical role in the urban planning of the mega scale development by providing public access to the Expo 2020 pavilions.